Identify the correct option regarding PERT and CPM.
The correct answer is C. In CPM, time estimates are uncertain but in PERT duration of each activity is known with certainty. You've hit your session limit · resets 5:20pm (America/New_York)
Question
Identify the correct option regarding PERT and CPM.
Options
- APERT and CPM are suitable for a situation which does not have a definite start and a definite end.
- BIn CPM, duration of each activity is known with certainty where in PERT it assumes a probability
- CIn CPM, time estimates are uncertain but in PERT duration of each activity is known with certainty.
- DPERT emphases both time and cost.
How the community answered
(43 responses)- A12% (5)
- B2% (1)
- C81% (35)
- D5% (2)
Explanation