nerdexam
Six_Sigma

ICBB · Question #249

Identify the correct option regarding PERT and CPM.

The correct answer is C. In CPM, time estimates are uncertain but in PERT duration of each activity is known with certainty. You've hit your session limit · resets 5:20pm (America/New_York)

Question

Identify the correct option regarding PERT and CPM.

Options

  • APERT and CPM are suitable for a situation which does not have a definite start and a definite end.
  • BIn CPM, duration of each activity is known with certainty where in PERT it assumes a probability
  • CIn CPM, time estimates are uncertain but in PERT duration of each activity is known with certainty.
  • DPERT emphases both time and cost.

How the community answered

(43 responses)
  • A
    12% (5)
  • B
    2% (1)
  • C
    81% (35)
  • D
    5% (2)

Explanation

You've hit your session limit · resets 5:20pm (America/New_York)

Community Discussion

No community discussion yet for this question.

Full ICBB Practice