A company has installed a system that prevents orders with incorrect information from being forwarded to production scheduling. This is an example of which of the following lean tools?

The correct answer is C. Poka-Yoke. A Poka-Yoke is a Japanese technique which means mistake proofing. It helps the mistakes from not being passed on to next operation.

Securing and Managing Campus Mobility Environments

Question

A company has installed a system that prevents orders with incorrect information from being forwarded to production scheduling. This is an example of which of the following lean tools?

Options

  • AStandard work
  • BKanban
  • CPoka-Yoke
  • DVisual factory

How the community answered

(43 responses)
  • A
    14% (6)
  • B
    5% (2)
  • C
    74% (32)
  • D
    7% (3)

Explanation

A Poka-Yoke is a Japanese technique which means mistake proofing. It helps the mistakes from not being passed on to next operation.

Topics

#Poka-Yoke#error proofing#mistake proofing#lean tools