Control Charts were developed by Dr. Shewhart to track data over time. To detect Special Cause variation the Control Charts use which of these?
The correct answer is C. Center Line and Control Limits. You've hit your session limit · resets 5:20pm (America/New_York)
Question
Control Charts were developed by Dr. Shewhart to track data over time. To detect Special Cause variation the Control Charts use which of these?
Options
- AData shift analysis
- BOutlier analysis methods
- CCenter Line and Control Limits
- DNone of the above
How the community answered
(19 responses)- A5% (1)
- B11% (2)
- C79% (15)
- D5% (1)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)