Which step should be taken after physically installing the servers in the data center during the installation process?

The correct answer is A. Configure the network connections. After physically installing the servers, the next step is to configure the network connections.

Implementing HPE Aruba Networking Data Center Solutions

Question

Which step should be taken after physically installing the servers in the data center during the installation process?

Options

  • AConfigure the network connections
  • BInstall the operating system
  • CRun system diagnostics
  • DPerform compatibility testing

How the community answered

(31 responses)
  • A
    81% (25)
  • B
    6% (2)
  • C
    10% (3)
  • D
    3% (1)

Explanation

After physically installing the servers, the next step is to configure the network connections.

Topics

#server installation#network configuration#data center deployment#installation process