Which step should be taken after physically installing the servers in the data center during the installation process?
The correct answer is A. Configure the network connections. After physically installing the servers, the next step is to configure the network connections.
Implementing HPE Aruba Networking Data Center Solutions
Question
Which step should be taken after physically installing the servers in the data center during the installation process?
Options
- AConfigure the network connections
- BInstall the operating system
- CRun system diagnostics
- DPerform compatibility testing
How the community answered
(31 responses)- A81% (25)
- B6% (2)
- C10% (3)
- D3% (1)
Explanation
After physically installing the servers, the next step is to configure the network connections.
Topics
#server installation#network configuration#data center deployment#installation process