HPE7-A04 · Question #76
You have a data center with 99.9% availability requirements. How many hours of downtime (unplanned) is allowed to meet this availability requirement?
The correct answer is D. 8.8 hours. Option D (8.8 hours) is correct because 99.9% availability means 0.1% downtime is permitted. Multiplying 8,760 hours (hours in a year) by 0.001 gives 8.76 hours, which rounds to 8.8 hours. Why the distractors are wrong: A (6.8 hours) corresponds to no standard availability tier…
Question
You have a data center with 99.9% availability requirements. How many hours of downtime (unplanned) is allowed to meet this availability requirement?
Options
- A6.8 hours
- B3.4 hours
- C8.6 hours
- D8.8 hours
How the community answered
(37 responses)- A3% (1)
- B8% (3)
- C3% (1)
- D86% (32)
Explanation
Option D (8.8 hours) is correct because 99.9% availability means 0.1% downtime is permitted. Multiplying 8,760 hours (hours in a year) by 0.001 gives 8.76 hours, which rounds to 8.8 hours.
Why the distractors are wrong:
- A (6.8 hours) corresponds to no standard availability tier - it's simply not the result of any common availability percentage calculation.
- B (3.4 hours) is approximately half the correct value, which would reflect ~99.96% availability, not 99.9%.
- C (8.6 hours) is close but slightly low - likely a rounding trap designed to catch off-by-one errors in the calculation.
Memory tip: Anchor on the formula - (1 − availability%) × 8,760. For each "nine" added (99% → 99.9% → 99.99%), divide the downtime by 10. Since 99% = 87.6 hours, one more nine gives 8.76 ≈ 8.8 hours.
Topics
Community Discussion