XYZ Regional Hospital is an integrated healthcare system of hospitals, neighborhood health centers, and small doctor offices. XYZ Regional Hospital has recently merged with 4x neighborhood health…

The correct answer is B. Kickoff the project to identify the team members involved, review the deliverables, expectations. Phase 1 of a network refresh project begins with the project kickoff, which includes defining team participation, reviewing objectives, deliverables, and timelines, and starting the discovery and data collection needed to drive the design process.

Gathering and Analyzing Business and Technical Requirements

Question

XYZ Regional Hospital is an integrated healthcare system of hospitals, neighborhood health centers, and small doctor offices. XYZ Regional Hospital has recently merged with 4x neighborhood health centers and 125 doctor branch offices. The wireless, wired access, and AAA solutions are outdated and need to be replaced. XYZ Regional Hospital is looking to future-proof and improve efficiency across all sites by enhancing wired and wireless access and migrating to a centralized and unified wired/wireless and policy management that can provide uninterrupted availability of all systems. Locations:

  • XYZ Regional Hospital is located in New York City
  • Dila Health Center is located in City A
  • Mount Health Center is located in City B
  • Rock Health Center is located in City C
  • Branch clinics are located at different locations across the United States

Requirements:

  • Provide, via management software, one single pane of glass to manage wired and wireless

LANs, and VPNs across campus, branch, and remote via web/cloud architecture providing near real-time insight, troubleshooting tools, and Service Level performance reporting.

  • Seamless integration across wired, wireless, WAN, SD-Branch, IoT
  • Provide secure wireless access to all the employees of the Regional Hospital and partners, as

well as provide wireless Internet access to medical citizens when they visit our facilities.

  • All-access points must support the following features and specifications: 802.11.ax (Wi-Fi 6E

Certified)

  • Security options including WP2/WPA3, 802.1X with Radius secure authentication
  • Identify and authenticate every wireless and wired device
  • End-to-end role-based security
  • Seamless mobility across the hospital for medical teams, patients, and visitors
  • Cuts Wi-Fi deployment times from days to hours and enables Zero-Touch deployments across

the site

  • Establishes a resilient, future-ready network infrastructure with the intelligence, scalability, and

intuitive toolsets to meet emerging needs

  • Fully redundant branch solution with dynamic path selection to the hospital

The hospital CIO is interested in reviewing the phase 1 approach and framework that will be used to achieve the goals of the network refresh project. What is the phase 1 task?

Options

  • AThe team will define and document a path for the current to future support model, including any
  • BKickoff the project to identify the team members involved, review the deliverables, expectations,
  • CReview the potential design options and further scope deployment efforts, phased implementation
  • DMeet with ITS Network/Telecom and support staff following the knowledge transfer sessions to

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    81% (38)
  • C
    11% (5)
  • D
    4% (2)

Explanation

Phase 1 of a network refresh project begins with the project kickoff, which includes defining team participation, reviewing objectives, deliverables, and timelines, and starting the discovery and data collection needed to drive the design process.