A customer requires new MCs for a large multi-site network with about 600 AP-535S ana 30,000 wireless clients. The customer requires redundancy for the MCs, with each MC being able to handle the…

The correct answer is D. The 7240XM MCs are required to support the large number of wireless clients in this network. See the full explanation below for the reasoning.

Question

A customer requires new MCs for a large multi-site network with about 600 AP-535S ana 30,000 wireless clients. The customer requires redundancy for the MCs, with each MC being able to handle the full toad in a failover situation. The network should be able to sustain the loss of a controller with stateful failover within seconds. It should be able to undergo software upgrades without downtime. The architect has recommended two 7240XM MCs. The customer points out that 7220

Options

  • BThe 724QXM MCs can support full CPSec tunnels with this number of APs. while the 7220 MCs cannot.
  • CThe 7240XM MCS provide a higher number of concurrent GRE tunnels to support 600APs with MCS in L2 clustering.
  • DThe 7240XM MCs are required to support the large number of wireless clients in this network

How the community answered

(18 responses)
  • B
    6% (1)
  • C
    17% (3)
  • D
    78% (14)