An HP Comware switch supports four MDCs. The operations of MDC 1, MDC 2, and MDC 3 are unreliable. The network administrator discovers that MDC 4 has very large routing tables. What is the first…

The correct answer is C. Assign a lower CPU weight to MDC 4. See the full explanation below for the reasoning.

Question

An HP Comware switch supports four MDCs. The operations of MDC 1, MDC 2, and MDC 3 are unreliable. The network administrator discovers that MDC 4 has very large routing tables. What is the first step the administrator should take to resolve the issues for MDC 1, 2, and 3?

Options

  • AAssign a storage limit to MDC 4.
  • BAssign a memory limit to MDC 4.
  • CAssign a lower CPU weight to MDC 4.
  • DAssign an absolute route limit to MDC 4.

How the community answered

(16 responses)
  • A
    13% (2)
  • C
    81% (13)
  • D
    6% (1)