HP
HPE0-V14 · Question #137
You are installing a server solution in a customer's data center. How can you ensure that the installation complies with relevant electrical best practices? (Choose two.)
The correct answer is B. Do not allow the overall system AC current load to exceed 80% of the branch circuit AC current D. Balance the server power load between available AC supply branch circuits. See the full explanation below for the reasoning.
Question
You are installing a server solution in a customer's data center. How can you ensure that the installation complies with relevant electrical best practices? (Choose two.)
Options
- AUse a single-phase, two-wire power receptacle with protective earth or ground (PE) to filter
- BDo not allow the overall system AC current load to exceed 80% of the branch circuit AC current
- CUse fanout cables when connecting the server to the network for maximum electrical impedance
- DBalance the server power load between available AC supply branch circuits
- EConfigure the server power to a single electrical circuit in the data center
How the community answered
(36 responses)- A6% (2)
- B78% (28)
- C14% (5)
- E3% (1)
Community Discussion
No community discussion yet for this question.