HP
HPE0-S51 · Question #95
You are installing a combined server and storage solution at a customer location. What must you keep in mind regarding the typical requirements for the location? (Choose two.)
See the full explanation below for the reasoning.
Question
You are installing a combined server and storage solution at a customer location. What must you keep in mind regarding the typical requirements for the location? (Choose two.)
Options
- ARoom temperature must not exceed 35 °C (95 °F)
- BRack tie kit should be installed on the rack for proper airflow
- CUPSs should be installed at the top of the rack for top mounted power feed
- DThere must be at least a 10 cm (4 in) clearance space at the front and back of the components
- ERack doors must be unlocked for easy component removal and maintenance
Community Discussion
No community discussion yet for this question.