A facility has several Gen9 Blade Systems, one of which failed. The integrator needs to configure an Active/Active configuration for high availability so the failure is avoided in the future. How…
The correct answer is C. 1 FlexFabric module, 2 Top of Rack switches. See the full explanation below for the reasoning.
Question
A facility has several Gen9 Blade Systems, one of which failed. The integrator needs to configure an Active/Active configuration for high availability so the failure is avoided in the future. How many FlexFabric modules and switches does the integrator need, at a minimum, to achieve this?
Options
- A2 FlexFabric modules, 1 Top of Rack switch
- B1 FlexFabric module, 1 data center switch
- C1 FlexFabric module, 2 Top of Rack switches
- D2 FlexFabric modules, 2 data center switches
How the community answered
(22 responses)- A5% (1)
- B9% (2)
- C86% (19)