nerdexam
HP

HPE0-S22 · Question #59

A cost-conscious customer needs a server upgrade to host a Citrix application virtualization solution. The solution must meet the following requirements: - Support 1,200 simultaneous users - Scale…

The correct answer is C. an HPE Moonshot Systems with m710 cartridges. See the full explanation below for the reasoning.

Question

A cost-conscious customer needs a server upgrade to host a Citrix application virtualization solution. The solution must meet the following requirements:

  • Support 1,200 simultaneous users
  • Scale out easily to accommodate 20 percent future growth
  • Provide optimum performance for applications such as Microsoft Office

Suite, Skype for Business, and Adobe Photoshop Which solution should the architect recommend?

Options

  • Aan HPE Moonshot System with m350 cartridges
  • Ban HPE Integrity Superdome X System with BL920s Gen8 blades
  • Can HPE Moonshot Systems with m710 cartridges
  • Dan HPE Integrity Superdome X System with BL920s Gen9 blades

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    11% (4)
  • C
    84% (32)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full HPE0-S22 Practice