HP
HPE0-S22 · Question #33
An architect reviews an HPE Apollo 6000 design and finds that there are plans for redundant iLO connections on each HPE Apollo 6000 chassis to a pair of top-of-rack switches. These switches are set…
The correct answer is D. Configure IRF between the top-of-rack switches. See the full explanation below for the reasoning.
Question
An architect reviews an HPE Apollo 6000 design and finds that there are plans for redundant iLO connections on each HPE Apollo 6000 chassis to a pair of top-of-rack switches. These switches are set up as individual switches connected to a single core. Which configuration change should the architect recommend to ensure a loop free management topology?
Options
- ARemove one iLO connection from each HPE Apollo 6000 chassis.
- BConfigure MAD between the top-of-rack switches.
- CReplace the top-of-rack switches with HPE Advanced Power Management Kits.
- DConfigure IRF between the top-of-rack switches.
How the community answered
(34 responses)- A9% (3)
- B3% (1)
- C3% (1)
- D85% (29)
Community Discussion
No community discussion yet for this question.