HPE0-J80 · Question #33
A storage architect is reviewing customer as-built documentation and a proposed design for an HPE 3PAR StoreServ deployment. The array must be installed in a co-location facility in facility…
The correct answer is A. The correct number of SAS Active Optical Cables (AOC) are required. See the full explanation below for the reasoning.
Question
A storage architect is reviewing customer as-built documentation and a proposed design for an HPE 3PAR StoreServ deployment. The array must be installed in a co-location facility in facility supplied and managed racks. The storage architect has determined that service clearances and power are adequate. The proposed design is storage-centric and will require two racks to accommodate all the disk enclosures. What should the storage architect consider when validating the bill of materials?
Options
- AThe correct number of SAS Active Optical Cables (AOC) are required
- BThe correct number of infiniBand cables are required
- CExpansion is only supported in HPE racks
- DThe correct number of Fiber Channel Cables are required
How the community answered
(38 responses)- A76% (29)
- B13% (5)
- C5% (2)
- D5% (2)