HP
HPE0-J79 · Question #28
A storage architect is reviewing customer as-built documentation and a proposed design for an HPE 3PAR StoreServ deployment. The array must be installed in a co-location facility in facility…
The correct answer is D. The correct number of SAS Active Optical Cables (AOC) are required. See the full explanation below for the reasoning.
Question
A storage architect is reviewing customer as-built documentation and a proposed design for an HPE 3PAR StoreServ deployment. The array must be installed in a co-location facility in facility- supplied and managed racks. The storage architect has determined that service clearances and power are adequate. The proposed design is storage-centric and will require two racks to accommodate all the disk enclosures. What should the storage architect consider when validating the bill of materials?
Options
- AExpansion is only supported in HPE racks
- BThe correct number of Infiniband cables are required.
- CThe correct number of Fibre Channel cables are required
- DThe correct number of SAS Active Optical Cables (AOC) are required
How the community answered
(42 responses)- A5% (2)
- B2% (1)
- C10% (4)
- D83% (35)
Community Discussion
No community discussion yet for this question.