HP2-T26 · Question #41

When installing half-height c-Class server blades in a c3000 rack enclosure, what is the recommended sequence for installing them into the server bays when viewed from the front of the enclosure?

The correct answer is D. from bottom to top, then left to right. See the full explanation below for the reasoning.

Question

When installing half-height c-Class server blades in a c3000 rack enclosure, what is the recommended sequence for installing them into the server bays when viewed from the front of the enclosure?

Options

  • Afrom top to bottom, then right to left
  • Bfrom bottom to top, then right to left
  • Cfrom top to bottom, then left to right
  • Dfrom bottom to top, then left to right

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    10% (2)
  • D
    80% (16)