When should a performance baseline be captured?
The correct answer is A. after the initial installation of the equipment, during normal daily operation. See the full explanation below for the reasoning.
Question
When should a performance baseline be captured?
Options
- Aafter the initial installation of the equipment, during normal daily operation
- Bafter the initial installation of the equipment, during peak operating conditions
- Cbefore and after each step of the initial installation of the equipment
- Dthree times a day during the first week following the initial installation of the equipment
How the community answered
(39 responses)- A79% (31)
- B5% (2)
- C3% (1)
- D13% (5)
Community Discussion