When should a performance baseline be captured?

The correct answer is C. after any hardware or software additions to the system. Industry Standard Architecture - Student Guide 2 - Page 217: Establishing a baseline This baseline should be captured after initial installation of the equipment, during normal daily operation. The baseline should be updated after any hardware or software additions to the

Common IT Terminology, Standards, and Best Practices

Question

When should a performance baseline be captured?

Options

  • Aafter updating the server ROM
  • Bduring the peak server usage
  • Cafter any hardware or software additions to the system
  • Dafter replacing a failed component

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    4% (1)
  • C
    74% (20)
  • D
    7% (2)

Explanation

Industry Standard Architecture - Student Guide 2 - Page 217: Establishing a baseline This baseline should be captured after initial installation of the equipment, during normal daily operation. The baseline should be updated after any hardware or software additions to the