Which statement is correct about using the Guided Maintenance (GM) scripts on an HP 3PAR StoreServ system?
The correct answer is D. The Controller Node and drive cage cannot be removed and replaced by using the GM scripts. Use Guided Maintenance when servicing the following hardware components: - Controller node - Time of day battery
HP 3PAR StoreServ Troubleshooting and Repair
Question
Which statement is correct about using the Guided Maintenance (GM) scripts on an HP 3PAR StoreServ system?
Options
- AThe GM scripts have to be run on a 3PARsvc to replace the drive chassis midplane.
- BThe Service Processor and node clock battery cannot be removed and replaced by using the GM
- CThe GM scripts have to be run on a 3PARsvc to replace the Service Processor.
- DThe Controller Node and drive cage cannot be removed and replaced by using the GM scripts.
How the community answered
(17 responses)- A6% (1)
- B6% (1)
- C12% (2)
- D76% (13)
Explanation
Use Guided Maintenance when servicing the following hardware components: - Controller node - Time of day battery
Topics
#Guided Maintenance#GM scripts#hardware replacement#drive cage