HP0-Y50 · Question #76
An implementation plan should include an agreed-on time for the final rollback decision. What should this decision be scheduled?
The correct answer is C. just before the point of no return, which is calculated by subtracting the rollback time from the end. See the full explanation below for the reasoning.
Question
An implementation plan should include an agreed-on time for the final rollback decision. What should this decision be scheduled?
Options
- AAfter the cutover to the new solution and the first set of validation tests and just before the user
- Bafter the first steps of the rollback plan have been implemented, about ten minutes before the end
- Cjust before the point of no return, which is calculated by subtracting the rollback time from the end
- Dten minutes before the end of the maintenance window or one hour into the implementation, whichever
How the community answered
(47 responses)- A15% (7)
- B4% (2)
- C74% (35)
- D6% (3)
Community Discussion
No community discussion yet for this question.