HP0-Y50 · Question #42

HP0-Y50 Question #42: Real Exam Question with Answer & Explanation

Sign in or unlock HP0-Y50 to reveal the answer and full explanation for question #42. The question stem and answer options stay visible for context.

Question

A company is upgrading a data center network solution in phases. The first phase involves updating the top of rack (ToR) switches in one rack. Other switches will be updated in their phases. What is one benefit of this approach?

Options

  • AIt allows the through testing of the solution in real-world circumstances
  • BIt ensures that the network can be updated without any scheduled downtime
  • CIt removes the need to conduct connectivity and failover tests during the implementation
  • DIt removes the need for working with customer change management processes