HP0-Y50 · Question #42

A company is upgrading a data center network solution in phases. The first phase involves updating the top of rack (ToR) switches in one rack. Other switches will be updated in their phases. What is…

The correct answer is C. It removes the need to conduct connectivity and failover tests during the implementation. See the full explanation below for the reasoning.

Question

A company is upgrading a data center network solution in phases. The first phase involves updating the top of rack (ToR) switches in one rack. Other switches will be updated in their phases. What is one benefit of this approach?

Options

  • AIt allows the through testing of the solution in real-world circumstances
  • BIt ensures that the network can be updated without any scheduled downtime
  • CIt removes the need to conduct connectivity and failover tests during the implementation
  • DIt removes the need for working with customer change management processes

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    4% (1)
  • C
    74% (17)
  • D
    9% (2)

Community Discussion

No community discussion yet for this question.