HP0-Y45 · Question #36

A network architect has planned several validation tests and user acceptance tests (UATs) for a new HP solution. In order to ensure meaningful results, what is one step that the network architect…

The correct answer is A. Talk with key stakeholders to determine valid maintenance windows for the UATs. See the full explanation below for the reasoning.

Question

A network architect has planned several validation tests and user acceptance tests (UATs) for a new HP solution. In order to ensure meaningful results, what is one step that the network architect should complete before implementing the new solution?

Options

  • ATalk with key stakeholders to determine valid maintenance windows for the UATs.
  • BSchedule a point of no return, after which results will not be accepted.
  • CRun the same tests on the existing network solution.
  • DPlan how long it will take to rollback the new solution if the tests indicate poor results.

How the community answered

(23 responses)
  • A
    83% (19)
  • B
    4% (1)
  • C
    9% (2)
  • D
    4% (1)