You are planning to replace Cisco distribution layer switches with HP A-Series switches, and you are selecting a general strategy for the migration process. The strategy you select is to connect the…

See the full explanation below for the reasoning.

Question

You are planning to replace Cisco distribution layer switches with HP A-Series switches, and you are selecting a general strategy for the migration process. The strategy you select is to connect the new switches in parallel to the existing network. You will move the edge switch connections to the new distribution switches during the migration, as shown in the exhibit on page 5. What is a disadvantage of this strategy?

Options

  • AYou must disable Spanning Tree on all edge switches until you have finished migrating edge switches, connecting to the new distribution switches, which might introduce temporary broadcast storms.
  • BYou must migrate the routing functionality for every VLAN simultaneously so you cannot access how the migration is working for a single VLAN before completing the migration.
  • CThe connection between the existing distribution switches and the parallel network might become a bottleneck during the migration process unless you plan sufficient bandwidth.