HP0-Y37 · Question #16

The exhibit displays the basic steps in one migration process for replacing Cisco distribution layer switches with HP E-Series switches. For which of these customers would this method be acceptable?

The correct answer is C. The customer has scheduled a network outage in order to update the software on the Cisco edge switches. See the full explanation below for the reasoning.

Question

The exhibit displays the basic steps in one migration process for replacing Cisco distribution layer switches with HP E-Series switches. For which of these customers would this method be acceptable?

Options

  • AThe customer cannot tolerate more than twenty seconds of downtime for any given endpoint.
  • BThe customer wants you to have the E-Series switches route traffic for one VLAN for a test period before assuming all routing functions.
  • CThe customer has scheduled a network outage in order to update the software on the Cisco edge switches.
  • DThe customer has requested that you migrate the edge switches Layer 2 connections and test that functionality before the Layer 3 migration.

How the community answered

(54 responses)
  • A
    2% (1)
  • B
    9% (5)
  • C
    83% (45)
  • D
    6% (3)