While creating a baseline tor the Gen9 blades in a new c7000 BladeSystem Enclosure in an active/active configuration, the integrator determines that one blade has an NIC teaming setting of fail…

The correct answer is A. East/West bandwidth will be reduced few this server. Server-to-server traffic (east/west) in the enclosure will be reduced. Note: An active/active configuration is an Ethernet network configuration that allows active traffic on the same VLAN on multiple interconnect modules. The NICs on all the servers in the enclosure have their…

Changes in Virtual Connect and FlexFabric Integration

Question

While creating a baseline tor the Gen9 blades in a new c7000 BladeSystem Enclosure in an active/active configuration, the integrator determines that one blade has an NIC teaming setting of fail over. What will be the outcome of this setting in an active/active high availability configuration?

Options

  • AEast/West bandwidth will be reduced few this server.
  • BNetwork bandwidth will not be redundant for this server.
  • CNorth/South bandwidth will be reduced for this server.
  • DDownstream bandwidth will not be affected.

How the community answered

(33 responses)
  • A
    82% (27)
  • B
    3% (1)
  • C
    12% (4)
  • D
    3% (1)

Explanation

Server-to-server traffic (east/west) in the enclosure will be reduced. Note: An active/active configuration is an Ethernet network configuration that allows active traffic on the same VLAN on multiple interconnect modules. The NICs on all the servers in the enclosure have their NICs connected to adjacent HP Virtual Connect modules. All uplinks are active to forward network traffic. active-standby-about-fusion.html