What is the sequence to power on and power off a ProLiant server with external storage?
The correct answer is B. Power down the ProLiant first; power on the storage first. See the full explanation below for the reasoning.
Question
What is the sequence to power on and power off a ProLiant server with external storage?
Options
- APower down the storage first; power on the storage first.
- BPower down the ProLiant first; power on the storage first.
- CPower down the storage first, power on the storage first.
- DPower down the ProLiant first; power on the ProLiant first.
How the community answered
(30 responses)- A3% (1)
- B70% (21)
- C17% (5)
- D10% (3)