HP0-S44 · Question #28
A server integrator determines that power supply units (PSUs) are failing during the installation of new IT equipment at a specific customer site. Based on the HP 6-Step Troubleshooting Methodology…
The correct answer is B. Verify the utility voltage at the outlet before plugging the power cord of the PSU into that outlet. See the full explanation below for the reasoning.
Question
A server integrator determines that power supply units (PSUs) are failing during the installation of new IT equipment at a specific customer site. Based on the HP 6-Step Troubleshooting Methodology, what should the integrator do?
Options
- AVerify the current rating of the fuse feeding the power outlet.
- BVerify the utility voltage at the outlet before plugging the power cord of the PSU into that outlet
- CCheck the data center site for electromagnetic radiation (EMC).
- DTest new hardware in a staging area before installing the hardware in the computer room.
How the community answered
(33 responses)- A12% (4)
- B79% (26)
- C6% (2)
- D3% (1)