HP
HP0-S41 · Question #118
When a blade is inserted into a bay that has a VCM profile assigned, which action will the VCM perform before the server is allowed to power on?
The correct answer is C. Configure the NIC ports with profile provided MAC addresses. See the full explanation below for the reasoning.
Question
When a blade is inserted into a bay that has a VCM profile assigned, which action will the VCM perform before the server is allowed to power on?
Options
- ADetermine the Server OS
- BDownload new firmware update
- CConfigure the NIC ports with profile provided MAC addresses
- DCheck the embedded teaming configuration
How the community answered
(42 responses)- A7% (3)
- B14% (6)
- C74% (31)
- D5% (2)
Community Discussion