nerdexam
HP

HP0-S36 · Question #3

A customer with a limited budget is planning to implement critical business unit. The company is projecting variable growth. The result of the system sizing, in an initial phase, is a solution…

The correct answer is B. HP c3000 enclosure with one OA, redundant Ethernet switches, and eight BL460c servers. See the full explanation below for the reasoning.

Question

A customer with a limited budget is planning to implement critical business unit. The company is projecting variable growth. The result of the system sizing, in an initial phase, is a solution containing eight servers with dual processors. Which BladeSystem supports the customer's needs?

Options

  • AHP c7000 enclosure with one OA, redundant Ethernet switches, and eight BL460c Gen8 servers
  • BHP c3000 enclosure with one OA, redundant Ethernet switches, and eight BL460c servers
  • CHP c7000 enclosure with one OA, redundant Ethernet switch, and fully populated with BL460c Gen8
  • DHP c3000 enclosure with one OA, one Ethernet switch and fully populated with BL460c Gen8 servers

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    76% (26)
  • C
    3% (1)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full HP0-S36 Practice