HP
HP0-S36 · Question #3
A customer with a limited budget is planning to implement critical business unit. The company is projecting variable growth. The result of the system sizing, in an initial phase, is a solution…
The correct answer is B. HP c3000 enclosure with one OA, redundant Ethernet switches, and eight BL460c servers. See the full explanation below for the reasoning.
Question
A customer with a limited budget is planning to implement critical business unit. The company is projecting variable growth. The result of the system sizing, in an initial phase, is a solution containing eight servers with dual processors. Which BladeSystem supports the customer's needs?
Options
- AHP c7000 enclosure with one OA, redundant Ethernet switches, and eight BL460c Gen8 servers
- BHP c3000 enclosure with one OA, redundant Ethernet switches, and eight BL460c servers
- CHP c7000 enclosure with one OA, redundant Ethernet switch, and fully populated with BL460c Gen8
- DHP c3000 enclosure with one OA, one Ethernet switch and fully populated with BL460c Gen8 servers
How the community answered
(34 responses)- A15% (5)
- B76% (26)
- C3% (1)
- D6% (2)
Community Discussion
No community discussion yet for this question.