nerdexam
HP

HP0-S35 · Question #194

A customer is running a VMware DRS cluster with vMotion enabled in a business critical production environment. Which Step should be performed before servicing an HP server blade that is part of this…

The correct answer is C. Place the host that needs to be serviced in maintenance mode. See the full explanation below for the reasoning.

Question

A customer is running a VMware DRS cluster with vMotion enabled in a business critical production environment. Which Step should be performed before servicing an HP server blade that is part of this cluster to avoid virtual machine downtime?

Options

  • APower off all virtual machines in the environment
  • BSuspend the Virtual machines on the host that needs to be serviced.
  • CPlace the host that needs to be serviced in maintenance mode.
  • DPower off the server Blade before removing it from the enclusure.

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    71% (24)
  • D
    21% (7)

Community Discussion

No community discussion yet for this question.

Full HP0-S35 Practice