When installing a Modular Colling System (MCS) G2, which safely considerations must be implemented? (Select two)

Options

  • AInstall the MCS G2 free of the adjacent racks
  • BPlug the power supply cables for the MCS G2 in grounded sockets
  • CVerify the maximum water pressure in the MCS G2 does not exced 0.4 bar (6 PSI)
  • DUse aluminum piping for the water supply
  • EAttach the MCS G2 rack to the grouding system
  • FVefify the temperature inside the MCS G2 does not exceed 20 degress Celsius (68 Fahrengeit)