You are the QA manager for a company, working on a new project. In the past, end users have claimed that IT does not deliver what they ask for. For this release, you decide the end users will sign…

The correct answer is A. Baseline. See the full explanation below for the reasoning.

Question

You are the QA manager for a company, working on a new project. In the past, end users have claimed that IT does not deliver what they ask for. For this release, you decide the end users will sign off on all the requirements. Which feature enables the manager of an HP Application Lifecycle Management project to define a snapshot of the requirements after they are signed off by users?

Options

  • ABaseline
  • BTraceability Matrix
  • CDocument Generator
  • DGraph Wizard

How the community answered

(38 responses)
  • A
    82% (31)