HP
HP0-J63 · Question #50
A customer is designing a new backup strategy. The current backup job takes 72 hours to complete a full backup of all data, causing a performance impact when the job runs into business hours. What…
The correct answer is C. weekly full backups E. nightly incremental backups. See the full explanation below for the reasoning.
Question
A customer is designing a new backup strategy. The current backup job takes 72 hours to complete a full backup of all data, causing a performance impact when the job runs into business hours. What should the company implement to reduce the business impact of the backup job? (Select two.)
Options
- Aload balancing
- Badditional backup media
- Cweekly full backups
- Dbandwidth linits
- Enightly incremental backups
How the community answered
(51 responses)- A14% (7)
- B6% (3)
- C76% (39)
- D4% (2)
Community Discussion
No community discussion yet for this question.