When designing a solution, what defines the maximum tolerable amount of data loss from an IT service due to a major incident?

The correct answer is C. RPO. See the full explanation below for the reasoning.

Question

When designing a solution, what defines the maximum tolerable amount of data loss from an IT service due to a major incident?

Options

  • ASLO
  • BRTO
  • CRPO
  • DSLA

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    4% (1)
  • C
    69% (18)
  • D
    12% (3)