You have the responsibility of designing an entire information system. You design a chart to ensure the project gets completed on time. Your chart is based on the chart shown below. Which of the…

The correct answer is A. PERT Diagram. See the full explanation below for the reasoning.

Question

You have the responsibility of designing an entire information system. You design a chart to ensure the project gets completed on time. Your chart is based on the chart shown below. Which of the following types of project management tools have you created for your project?

Exhibit

HIT-001 question #517 exhibit

Options

  • APERT Diagram
  • BCritical Path
  • CGantt Chart
  • DVenn Diagram

How the community answered

(35 responses)
  • A
    80% (28)
  • B
    3% (1)
  • C
    6% (2)
  • D
    11% (4)