Which of the following defines the amount of time a project should take to complete?

The correct answer is C. Critical Path. See the full explanation below for the reasoning.

Question

Which of the following defines the amount of time a project should take to complete?

Options

  • APERT Diagram
  • BGantt Chart
  • CCritical Path
  • DVenn Diagram

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    15% (4)
  • C
    73% (19)
  • D
    4% (1)