CompTIA
HIT-001 · Question #445
Which of the following defines the amount of time a project should take to complete?
The correct answer is C. Critical Path. See the full explanation below for the reasoning.
Question
Which of the following defines the amount of time a project should take to complete?
Options
- APERT Diagram
- BGantt Chart
- CCritical Path
- DVenn Diagram
How the community answered
(26 responses)- A8% (2)
- B15% (4)
- C73% (19)
- D4% (1)
Community Discussion
No community discussion yet for this question.