HIT-001 · Question #374

You are asked to install an entirely new information system for your facility. Your superiors inquire about your plan action for this project. You construct a table illustrating your timeline and…

The correct answer is B. Gantt Chart. See the full explanation below for the reasoning.

Question

You are asked to install an entirely new information system for your facility. Your superiors inquire about your plan action for this project. You construct a table illustrating your timeline and division of duties for the project based on the table shown below. What type of project management tool have you created for your project?

Exhibit

HIT-001 question #374 exhibit

Options

  • ACritical Path
  • BGantt Chart
  • CVenn Diagram
  • DPERT Diagram

How the community answered

(31 responses)
  • A
    13% (4)
  • B
    77% (24)
  • C
    6% (2)
  • D
    3% (1)