Which of the following is a project management tool that is characterized by circles connected by lines to indicate the sequence of event?
The correct answer is A. PERT Diagram. See the full explanation below for the reasoning.
Question
Which of the following is a project management tool that is characterized by circles connected by lines to indicate the sequence of event?
Options
- APERT Diagram
- BGantt Chart
- CVenn Diagram
- DCritical Path
How the community answered
(40 responses)- A85% (34)
- B3% (1)
- C3% (1)
- D10% (4)