Which of the following project management tools consists of a table that contains horizontal time lines and vertical indicators of project components, with bars indicating when and by whom tasks are…
The correct answer is B. Gantt Chart. See the full explanation below for the reasoning.
Question
Which of the following project management tools consists of a table that contains horizontal time lines and vertical indicators of project components, with bars indicating when and by whom tasks are to be completed?
Options
- ACritical Path
- BGantt Chart
- CVenn Diagram
- DPERT Diagram
How the community answered
(34 responses)- A3% (1)
- B82% (28)
- C3% (1)
- D12% (4)