Question
You are asked to install a completely new information system for your facility. Your superiors inquire how long the project will take. You construct a chart illustrating how long the project will take. You design a chart based on the one shown below. Which of the following types of project management tools have you created to illustrate the time of completion for your project?
Exhibit
Options
- APERT Diagram
- BGantt Chart
- CVenn Diagram
- DCritical Path
How the community answered
(44 responses)- A5% (2)
- B11% (5)
- C7% (3)
- D77% (34)