HIT-001 · Question #185

You have the responsibility of setting up an entire information system for your facility. Any member of the team can perform any task as long as the project gets completed in an efficient manner…

The correct answer is C. Parallel. See the full explanation below for the reasoning.

Question

You have the responsibility of setting up an entire information system for your facility. Any member of the team can perform any task as long as the project gets completed in an efficient manner. Which of the following describes the division of workload you have assigned?

Options

  • AUnilateral
  • BUnit Assembly
  • CParallel
  • DSerial

How the community answered

(33 responses)
  • A
    18% (6)
  • B
    6% (2)
  • C
    73% (24)
  • D
    3% (1)