HH0-340 · Question #43
Which three key metrics are needed for sizing industry standard applications? (Choose three.)
The correct answer is A. IO read/write ratios C. IO rates and data transfer rates D. cache read hit ratios. See the full explanation below for the reasoning.
Question
Which three key metrics are needed for sizing industry standard applications? (Choose three.)
Options
- AIO read/write ratios
- Bport speed
- CIO rates and data transfer rates
- Dcache read hit ratios
- Enumber of ACP/BED pairs
How the community answered
(40 responses)- A78% (31)
- B8% (3)
- E15% (6)
Community Discussion