A customer has a three data center (3DC) with delta resync configuration running a TrueCopy link and an HUR link. The primary site fails and they want to fail over to the TrueCopy secondary site…
The correct answer is A. They must run a horctakeover at the TrueCopy S-Vol site. D. An initial copy of the HUR delta resync is not required. See the full explanation below for the reasoning.
Question
A customer has a three data center (3DC) with delta resync configuration running a TrueCopy link and an HUR link. The primary site fails and they want to fail over to the TrueCopy secondary site. Which two statements are true? (Choose two.)
Options
- AThey must run a horctakeover at the TrueCopy S-Vol site.
- BThey must run a horctakeover at the TrueCopy P-Vol site.
- CAn initial copy of the HUR delta resync must be performed.
- DAn initial copy of the HUR delta resync is not required.
How the community answered
(28 responses)- A75% (21)
- B14% (4)
- C11% (3)
Community Discussion