Hitachi
HH0-300 · Question #69
A customer is using Hitachi Universal Replicator (HUR) on a VSP. The customer has an 8 hour replication network outage which exceeds the HUR journal capacity. HUR suspends in error. What is the…
The correct answer is B. The HUR S-Vol is usable. See the full explanation below for the reasoning.
Question
A customer is using Hitachi Universal Replicator (HUR) on a VSP. The customer has an 8 hour replication network outage which exceeds the HUR journal capacity. HUR suspends in error. What is the status of the HUR S-Vol?
Options
- AThe HUR S-Vol is unusable.
- BThe HUR S-Vol is usable.
- CHUR requires an initial copy.
- DHUR needs to be reconfigured
How the community answered
(56 responses)- A5% (3)
- B79% (44)
- C13% (7)
- D4% (2)
Community Discussion