Hitachi
HH0-300 · Question #38
A customer has stated several disaster recovery objectives. The acceptable data loss is 4 hours. They must have their systems operational within 7 hours of a disaster. They must also have three…
The correct answer is B. 4 hours. See the full explanation below for the reasoning.
Question
A customer has stated several disaster recovery objectives. The acceptable data loss is 4 hours. They must have their systems operational within 7 hours of a disaster. They must also have three copies of the data at the recovery site. What is the customer's recovery point objective?
Options
- A3 hours
- B4 hours
- C7 hours
- D11 hours
How the community answered
(39 responses)- A3% (1)
- B77% (30)
- C13% (5)
- D8% (3)
Community Discussion