nerdexam
Hitachi

HH0-300 · Question #38

A customer has stated several disaster recovery objectives. The acceptable data loss is 4 hours. They must have their systems operational within 7 hours of a disaster. They must also have three…

The correct answer is B. 4 hours. See the full explanation below for the reasoning.

Question

A customer has stated several disaster recovery objectives. The acceptable data loss is 4 hours. They must have their systems operational within 7 hours of a disaster. They must also have three copies of the data at the recovery site. What is the customer's recovery point objective?

Options

  • A3 hours
  • B4 hours
  • C7 hours
  • D11 hours

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    77% (30)
  • C
    13% (5)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.

Full HH0-300 Practice