An RPO of six hours has been defined for a site-wide disaster. Which two actions should be performed to achieve the selected RPO? (Choose two.)
The correct answer is A. Bandwidth should be sized to a six hour peak rolling average. C. Point-in-time copies should be created every six hours at the recovery site. See the full explanation below for the reasoning.
Question
An RPO of six hours has been defined for a site-wide disaster. Which two actions should be performed to achieve the selected RPO? (Choose two.)
Options
- ABandwidth should be sized to a six hour peak rolling average.
- BPoint-in-time copies should be created every six hours at the production site.
- CPoint-in-time copies should be created every six hours at the recovery site.
- DNightly backup tapes should be taken offsite daily.
How the community answered
(33 responses)- A76% (25)
- B6% (2)
- D18% (6)
Community Discussion