You are working on a Business Continuity plan for a customer. The customer states, "This business process is important for us but we can afford one hour data loss and two hours are tolerable to…

The correct answer is B. The business recovery time objective is two hours. C. The business process recovery point objective is one hour. See the full explanation below for the reasoning.

Question

You are working on a Business Continuity plan for a customer. The customer states, "This business process is important for us but we can afford one hour data loss and two hours are tolerable to recover." Which two statements correctly reflect the business process requirements? (Choose two.)

Options

  • AThe business recovery time objective is one hour.
  • BThe business recovery time objective is two hours.
  • CThe business process recovery point objective is one hour.
  • DThe business process recovery point objective is two hours.

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    70% (23)
  • D
    21% (7)