Your customer must establish a Three Data Center (3DC) Business Continuity Solution using Universal Storage Platform (USP) systems. Which three tasks are required to setup the solution? (Choose…
The correct answer is A. Enable bi-directional paths between local and distant USPs. D. Enable bi-directional Fibre Channel links between the primary and local USPs. E. Implement Journal Groups of equal size and performance on local and distant USPs. See the full explanation below for the reasoning.
Question
Your customer must establish a Three Data Center (3DC) Business Continuity Solution using Universal Storage Platform (USP) systems. Which three tasks are required to setup the solution? (Choose three.)
Options
- AEnable bi-directional paths between local and distant USPs.
- BUpgrade the shared memory size of the local and distant USPs.
- CUpgrade the shared memory size on all three USPs by 25 percent.
- DEnable bi-directional Fibre Channel links between the primary and local USPs.
- EImplement Journal Groups of equal size and performance on local and distant USPs.
How the community answered
(50 responses)- A72% (36)
- B8% (4)
- C20% (10)