You are in the planning phase for a file system migration. What are two considerations for planning the migration window of the initial and incremental copy phases? (Choose two.)

The correct answer is B. available network bandwidth D. CPU/IO resources on the source file servers. See the full explanation below for the reasoning.

Question

You are in the planning phase for a file system migration. What are two considerations for planning the migration window of the initial and incremental copy phases? (Choose two.)

Options

  • Anumber of clients
  • Bavailable network bandwidth
  • Cnumber of shares/exports
  • DCPU/IO resources on the source file servers

How the community answered

(42 responses)
  • A
    7% (3)
  • B
    81% (34)
  • C
    12% (5)