Hitachi
HH0-240 · Question #82
Which three steps should be performed during a new HUS VM installation? (Choose three.)
The correct answer is B. Provision and configure the system. D. Connect the CE laptop to the Console LAN connection port on the SVP. E. Enable user accounts and software licenses. See the full explanation below for the reasoning.
Question
Which three steps should be performed during a new HUS VM installation? (Choose three.)
Options
- AInstall HiTrack Monitor on a customer server and configure it.
- BProvision and configure the system.
- CInstall SVP jumpers.
- DConnect the CE laptop to the Console LAN connection port on the SVP.
- EEnable user accounts and software licenses .
How the community answered
(39 responses)- A13% (5)
- B82% (32)
- C5% (2)
Community Discussion
No community discussion yet for this question.